施工技术 2013年8月下 16 CONSTRUCTIONTECHNOLOGY 第42卷第16期 DOI:10.7672/sgjs2013160016 某钢-木混合结构拔柱设计与施工全过程监控技术* 李密,姜浩,郑昊 [摘要]某钢-木混合结构的老建筑1~2层为铸铁柱、钢梁结构,3~5层为木结构木格栅楼面,梁柱节点均为铰接 设计。
采用整浇刚性节点将1层4根铸铁柱拔除,并对施工进行全过程监控。
结果表明新增托梁应变、挠度均较 小,拔柱前后周边钢柱无新增倾斜及不均匀沉降,该设计方案及施工控制合理可行。
[关键词]加固;改造;托梁拔柱;监测 [中图分类号】TU391 [文献标识码]A [文章编号]1002-8498(2013)16-0016-03 DesignandWhole ConstructionProcessMonitoring ofa Steel-timber Composite Structure forRemoving Columns Li Mi,Jiang Hao,Zheng Hao (Shanghai Key Laboratory of New Technology for Engineering Structures,SRIBS,Shanghai 200032,China) Abstract:An old building with cast iron column and steel beams in the first and second floor, timber structure andwooden gridsfrom the third floor tofifthflooris designed by hinged joint detailsofbeams and columns.Themethod of integral pouring rigid joint is adopted to remove four columns in the first floor withwhole construction processmonitoring,which shows that the strain and deflectionof the new supporting beam is low and the inclination anduneven setlement of the steelcolumnsremainsalmostno changes before and after the construction of supporting beam and removing column,and it is reasonable and feasible for the design and construction monitoring. Key wordsstrengthening;reconstruction; supporting beam and removing column;monitoring 托梁拔柱是增大空间的常用改造方法,广泛适西方向单向布置的钢梁,3~5层为木结构,各层楼 用于工业和民用建筑,托梁拔柱需要考虑荷载传递面均为南北向布置的木格栅,且各层梁柱均为铰接 路线的转移、托梁支撑设计、周边柱及地基基础的 连接,底层层高为5.28m,因后期装修使用功能的改 加固设计以及施工阶段的承载力和稳定验算等。
变,需将1层4根柱拔除,改造成立体停车库,相应 通常托梁拔柱改造有2种方法:①拆除上部结构 的轴线跨度由原来的5.08m增加至10.16m,拔柱 (如单层工业建筑,拆除屋盖)或者支顶上部结构 平面如图1所示。
后,使待拔柱荷载转移到临时支撑,拔除柱后,加 12托梁拔柱设计方案 固、制作托梁,然后恢复上部结构或卸载实现荷载 该房屋整体结构内部为东西向布置的梁柱承 再次转移到托梁的方法;②先原位制作托梁,通过 重体系,且各层梁柱均为铰接节点,整体性较差,其 设计卸载装置将待拔柱上荷载转移到托梁,后拔除 中1,2层柱均为外包砖墙的铸铁柱,原铸铁柱1外 柱的方法。
按其施工方法的不同可分为有千斤 径254mm,壁厚38mm;原铸铁柱2外径229mm,壁 顶顶升的托梁拔柱和无千斤顶顶升的托梁拔柱。
厚32mm,截面尺寸均为470mm×470mm,铸铁柱标 1工程概况 高分别为±0.000~5.280m和5.280~9.340m。
铸 某5层老建筑建于1907年,内部为梁柱结构承铁柱顶部为U形柱托,柱托与上部铸铁柱采用盖板 重,周边为砖墙承重,其中1~2层为铸铁柱,梁为东 连接,钢梁穿U形柱托,且在柱中心位置断开,并采 用节点板连接,U形柱托两侧各布置2道耳...