施工技术2016年1月上 88CONSTRUCTIONTECHNOLOGY第45卷第1期 DOI:10.7672/sgjs2016010088
富水固结黏土层浅埋暗挖隧道工程实例研究
刘魁刚 (北京市轨道交通建设管理有限公司,北京100068)
[摘要]北京地区浅埋暗挖法隧道通常采用普通管井降水,但是对于裂隙发育的富水固结状黏土地层,由于地层中 裂隙的存在,垂直渗透系数和水平渗透系数差异巨大,普通管井降水半径小、形不成漏斗效应,效果极差。
需采取 地面井点降水结合隧道内明排的方式,才能保证隧道开挖及初期支护的质量、安全和施工效率。
[关键词]隧道工程;浅埋暗挖;降水;裂隙;渗透系数 [中图分类号】U455.4[文献标识码]A【文章编号】1002-8498(2016)01-0088-04 ResearchonShallowBuriedTunnelinWateryConsolidationClayLayer Liu Kuigang (Bejing MTRConstruction Administration Corporation,Bejing100068,China) Abstract:Ordinary well dewatering is usually used in Beijing when shallow tunnel by excavation. However, when it es to fractured water-rich consolidation of clay-like formations,owing to the existence of fissure in layer,verticalpermeability and horizontal permeability have huge difference,and ordinary well dewatering has small radius and can't form a funnel,resulting to the bad effect.In order to ensure the quality,safetyand construction efficiency of tunnel excavation inprimary support,measures like well-points dewatering on the ground bined with open-discharge inside the tunnel should be taken. Key words:tunnels;shallow tunnel by excavation;dewatering;cracks;permeability coefficient
0引言1工程概况 隧道洞室开挖时,地下水的存在会对软岩、土、1.1隧道结构形式及开挖方法 砂层造成不稳定和荷载增大,大量的地下水与高压隧道为单洞单线马蹄形断面,开挖断面面积约 水常会酿成洞内突水、突泥、突砂、地面沉降、地下为35.36m²,隧道单线长度557.8m,采用浅埋暗挖 水枯竭等重大事故。
根据相关规范规定及设计文法施工,隧道平均埋深11.4~17.6m。
隧道竖向以 件要求,浅埋暗挖的隧道必须无水作业,但实际施0.64%坡度自区间风井向南邵站爬升,南邵站处为 工时,尤其在富水地层中经常会遇到降水、止水难暗挖段高程最高点,区间风井为暗挖段最低点,区 度大等难题,在费用、工期等方面无法满足无水作间风井与废水泵房合建。
业要求,坚持要求实现无水作业并不现实。
正在修隧道结构采用复合式衬砌(初期支护+二次衬 建的北京地铁昌平线二期工程昌平新区站一南邵砌)。
初期支护由喷射混凝土、钢筋网及钢格栅(纵
地层(水平渗透系数和纵向渗透系数相差25倍以期支护与二次衬砌之间铺设EVA防水层。
超前支 上),无法实现无水作业。
经过多次专家论证,按要护采用直径32mm、壁厚3.25mm、长度2.5m的超前 求采取相应技术措施后,暗挖区间在带水作业环境小导管(环向间距0.3m,纵向间距1m,纵向搭接 下,安全、顺利地完成了隧道贯通,二衬封闭后进行1.5m)并预注浆,采用水泥单浆液。
初期支护背后 注浆,500多m的隧道没有出现渗漏点。
采用无收缩水泥浆液注浆回填。
隧道采用正台阶 预留核心土法开挖。
隧道剖面如图1所示。
[收稿日期]2015-08-12:[修订日期]2015-09-10[作者筒介]刘魁刚,高级工程师,E-mail:@qq.1.2工程地质及水文地质条件
隧道段属于山前冲积平原,其间分布东沙河一
万方数据
2016 No.1刘魁刚:富水固结黏土层浅埋...