施工技术2015年11月下 62CONSTRUCTIONTECHNOLOGY第44卷第22期 DOI:10. 7672/sgjs2015220062
江苏某大跨度高空钢连廊施工技术
张晓雄,张亚飞 (中亿丰建设集团股份有限公司,江苏苏州215000)
[摘要】江苏师范大学文化创意产业园文化创意大厦钢结构空中连廊位于75m以上高空。
该项目高度高,体量大, 质量要求高。
在结构安装过程中,采取了缆索吊装这一非常规吊装方法,通过科学、合理、可靠的技术论证和有效 的质量控制,成功地施工了该项工程,满足了施工和设计要求。
[关键词]钢结构;连廊;缆索;吊装;主索;垂度;施工技术 [中图分类号]TU758[文献标识码]A[文章编号]1002-8498(2015)22-0062-03 ConstructionTechnology of a Large-span Steel CorridorinHighSky inJiangsu ZhangXiaoxiong,ZhangYafei (Zhongyifeng Construction Group Co.,Ltd.,Suzhou,Jiangsu 215000, China) Abstract;Large-span steel corridor of Culture Creative Building in Culture Creative Industry Park of the Jiangsu Normal University locates at in 75m of high sky.The building has characteristics of high height, mass volume and high quality request. During installation of the building, the non-normal hoisting method of cable hoisting is used. By science,reasonable and reliable technique demonstration and effective quality control,the building is constructed successfully to meet the request of design and construction. Key words:steel structures; corridor; cable;hoists;main cable; dip; construction
1工程概况50kN,根本无法满足主梁的吊装要求。
因此要完成 江苏师范大学文化创意产业园文化创意大厦连廊结构的吊装,只能重新选择吊装方案。
钢结构空中连廊分为上下两层,底层标高75.230m,2.2方案确定 顶层标高80.030m,每层连廊长33.6m,宽14.8m,针对该工程钢结构跨度大、自重大、高度高等 面积约500m²,由5福主梁(H1000×45×16×25)特点并结合施工场地情况,结合以往类似工程的施 及梁间7根次梁(H450×200×8×16)构成(见图工经验和国内大跨度钢结构安装施工的工程实例, 1)。
主梁通过设置于混凝土柱牛腿上的抗震支座进行了多方案的比较分析。
目前国内大高度、大跨 与主体结构连接。
主梁跨度达到14.8m,每福主梁度、大吨位钢构件的非正常安装办法一般可采用拔 质量达到5t。
杆吊装、高空滑移、缆索吊装等方法。
各种吊装方 2方案选择法的特点和优缺点比较如表1所示。
2.1技术难点综合分析该工程的具体情况,结合各种吊装方 受到工程本身特点及现场施工条件的限制,连法的特点和优缺点,并考虑现有的机械设备情况、 廊东侧为5层裙房结构,西侧为大面积地下室顶板,施工工期等要求,我们认为高空滑移虽然最为经济 南北两侧为主体塔楼,四周均无法停放大型吊装设可靠,但仍未能解决构件垂直运输的技术难题;而 备,现场原有的塔式起重机设备,吊装范围内的极拔杆安装并不适用本项目大跨度结构构件的安装, 限吊装承载力仅为15kN,而连廊钢梁单福重达缆索吊装虽然在前期准备和施工工期的合理性上 [作者筒介]张晓雄,副总经理,高级工程师,E-mailzhangxiaoxiong@有局限,但却是最适应本工程特点的吊装方案。
最 zyfchina.终我司确定了缆索吊装这一施工方案。
[收稿日期]2015-08-17
万方数据
2015 No.22张晓雄等:江苏某大跨度高空钢连廊施工技术63
表1多种吊装方法对比 Table 1Comparing of hoisting methods 序号吊装方法特点优点缺点
...