施工技术 2013年4月上 12 CONSTRUCTIONTECHNOLOCY 第42卷第7期 DOI:10.7672/sgj82013070012 绿地中央广场局部逆作法施工技术* 蒋金生,温梦柯 (中天建设集团有限公司,浙江杭州310008) [摘要】由于业主要求,对某超高层建筑采用局部逆作法施工,1~4层钢结构及外框楼板先行施工,然后施工核心 简剪力墙体混凝土结构。
介绍了该方案的工艺原理和施工工艺流程,详细介绍了施工过程中的关键技术措施。
实 践结果表明,该技术的应用满足工程的进度和质量安全要求。
[关键词]高层建筑;逆作法;钢结构;临时支撑;施工技术 [中图分类号]TU745.1 【文献标识码】A [文章编号】1002-8498(2013)07-0012-03 PartialReversedConstructionTechnologyinthe CentralSquareofGreenLand Jiang Jinsheng,Wen Mengke (Zhongtian Consruction Group Co.,Lad.,Hangzhou,Zhejang310008,China) Abstract:Because of the requirements of the owner,partial reverse construction technology is adopted in a tall building.Steel structures and outside floor flab are constructed first and then concrete structure of core tube shear wall can be constructed. This paper introduced technical principle and process of this method,and then introduced in detail the key technical measures in construction.Engineering practice shows that the application of the method can meet the requirements of construction progress,quality and safety. Key words:tall buildings;reversed method;steel structures;temporary supports;construction 1工程概况 本工程位于郑州市郑东新区的核心区域郑州 综合交通枢纽西广场H地块,被城市绿地分割为南 北2个地块,为双塔超高层综合体建筑。
塔楼地下 4层,地上63层,基础底板底面埋深22.3m,总建筑 高度283.915m,塔楼结构形式为框架-核心筒-环带 桁架结构,由正四方形核心筒结构和20根型钢混凝 土劲性柱组成,主楼结构平面如图1所示。
本工程底板开始浇筑时间为2012年6月中旬, 此时业主为了满足工程预售的形象节点,提出在 图1主楼结构平面示意 2012年10月25日之前(约4个月时间)完成塔楼 Fig 1The structure plane of the main building 地上4层结构施工(即塔楼地上4层混凝土楼板浇 筑完毕)。
按照正常的施工工艺,即:核心筒钢结构 多方论证,最后采用1~4层钢结构及外框楼板先行 吊装一核心筒钢筋绑扎→核心筒爬模安装→核心 施工,后施工核心筒剪力墙体混凝土结构的方案。
筒混凝土浇筑→外框钢结构梁柱吊装→外框柱施 2工艺原理 工→外框混凝土楼板施工,需要近6个月时间才能 核心筒型钢柱从-7.100m开始安装,外框型钢 完成,显然需要对施工工艺进行改进和创新。
经过 柱从基础底板开始安装。
-7.100m以下按正常施 工工艺进行结构施工,核心筒混凝土结构施工至 浙江省建设厅科研项目:超高层建筑施工成套技术应用研究 [作者简介]蒋金生,总工程师,E-mail:@ -7.100m标高后,主要进行塔楼钢结构吊装,在钢 [收稿日期]2013-01-07 结构梁柱之间增加临时支撑梁以保证结构体系的 万方数据
2013 No.7 蒋金生等:绿地中央广场局部逆作法施工技术 13 稳定性。
钢结构吊装至16.800m标高(地上4层), 临时拉接钢梁在混凝土结构施工至该层时拆除。
铺设地上4层外框压型钢板,并浇筑钢筋混凝土楼 由于核心筒混凝土结构尚未施工,外框水平钢 板。
在钢结构吊装间隙,进行-7.100m以上核心筒 梁在核心筒一端无法与核心筒连接,核心筒内增加 ...