施工技术2014年4月上 110CONSTRUCTIONTECHNOLOGY第43卷第7期 DOI:10. 7672/sgjs2014070110 柔性钢梁大跨顶推关键技术研究*
马重刚,谢小飞,雷夏林 (中建三局建设工程股份有限公司工程总承包公司,湖北武汉430070) [摘要】武汉江汉六桥主桥为钢混组合梁的自锚式悬索桥,钢梁为双边主梁,采用顶推法施工,最大顶推跨径为 90m。
施工中结合钢梁结构形式与顶推设备特点,优化临时措施及增设背撑结构以减小最大顶推跨径时导梁前端 挠度,调整各临时支点高程保证梁段拼装线型和导梁无措施上墩。
工程结果表明,各项指标精度均满足设计要求。
[关键词]桥梁工程;钢梁;顶推技术;背撑结构;模拟分析 【中图分类号】U445.462【文献标识码】A[文章编号】1002-8498(2014)07-0110-04 ResearchonLarge-spanIncrementalLaunchingTechnology ofFlexibleSteelGirder Ma Zhonggang,Xie Xiaofei,Lei Xialin (General Construction Company of CCTEB,Wuhan,Hubei 430070,China) Abstract;The main bridge of the Sixth Hanjiang River bridge in Wuhan is a self-anchored suspension bridge with a steel and concrete bination girder which using incremental launching method. The largest span of incremental launching is 90 meters. Considering the girder structure and incremental launching device characterisics,which optimizing temporary measures and adding back support structure to reduce the deflection of guiding beam in maximum incremental launching span.Adjusting the temporary support elevation beam assembly line and ensure none measures to guiding beam. Engineering practice shows that it can meet the requirement of the design. Key words:bridges; steel girder; incremental launching technology;back support structure; simulations 顶推法是指在桥台的后方设置施工场地,将梁武汉江汉六桥是武汉市首座自锚式悬索桥,跨、 体在桥头施工场地逐段浇筑或拼装,用千斤顶纵向径布置为110m+252m+110m=452m,两侧增设 顶推,使梁体借助滑道或滑块,逐段或整段向前顶48m+57m压重跨,主桥钢梁总重达7000t。
其中2× 推,就位后落梁的施工方法。
顶推法具有桥梁节段(48+57+16.5)m采用预应力混凝土箱梁结构,其 固定在一个场地预制,可不中断交通或通航等特余均采用边主梁形式的钢-混凝土结合梁。
主梁采 点。
顶推法广泛适用于深谷和宽深河道上的桥梁、用边主梁形式的钢-混凝土结合梁,桥梁中心线处梁 高架桥以及等曲率曲线桥建设,混凝土箱梁及钢箱高3.56m,全宽(包括风嘴)42.8m,设有双向2.3% 梁均可采用逐段拼装并顶推施工。
的横坡,主梁布置如图1所示。
。
武汉江汉六桥主梁为三跨双边主梁的钢混结2顶推方案确定 构主梁,钢结构主梁采用平面框架体系,为不影响2.1顶推平台地址选择 汉江通航,钢梁采用顶推法施工,江中设置3组临时武汉江汉六桥采用一跨过江形式,2个主塔布 墩,为满足通航需求,临时墩最大间距为90m。
对于置在防洪大堤旁,汉口侧塔柱局防洪挡墙约140m, 这种柔性钢梁结构采用顶推法施工且顶推跨径达汉阳侧塔柱距离防洪大堤约50m。
汉阳侧堤内施工 90m,其技术要求高、施工难度大。
作业区域条件较差,而汉口侧施工作业区域较为良 1工程概况好,对比分析如图2所示。
图2a中,场地经过平整后,高程为+26.000m, *中建三局课题:大跨度柔性钢梁顶推...