2015年1月上施工技术 第44卷第1期CONSTRUCTIONTECHNOLOGY DO1;10.7672/sgjs2015010003
带地下室建筑地面预筑弹性顶托微差下沉 施工技术研究*
张琨 (中建三局集团有限公司技术中心,潮北武汉430070) [摘要]介绍了一种带地下室多高层建筑地面预筑、弹性顶托、微差下沉施工方法,简称“预筑落成法”,即地下室在 地面预筑,利用在建结构自身作为基坑支护,使用弹性顶托装置实现建筑物微差下沉,将建筑物均匀下沉至预定标 高后,与工程桩嵌固。
该方法避免了临时支护结构,实现上下同步施工,缩短工期。
[关键词】预筑落成法;弹性顶托;微差下沉;同步施工 [中图分类号】TU7533[文献标识码】A【文章编号】1002-8498(2015)01-0003-04 Research on the High-rise Buildings with Basement that Pre-buildon theGroundand Gradual SaggingbyJacks Zhang Kun (Technology Center of China Construetion Third Engineering Bureau Co.,Lud., Wuhan,Hubei 430070,China) Abstract:This paper introduced a construction method of high-rise buildings with the basement,that was abbreviated as“pre-build subsidence”. The building was pleted in ground and gradual sagging by the jacks,made use of the building structure itself as foundation excavation supporting structure. The building was fixed on the engineering piles when sinks to the seting elevation. This method avoids the temporary support structure, and the synchronous construction on the ground and underground were achieved, the construction period is shorten. Key words:pre-build subsidence;elastic jacking; gradual sagging; synchronous construction 1研究背景托、微差下沉施工技术,简称“预筑落成法”。
该技 目前,带地下室房屋建造基本遵循地下工程、术研究及下沉工艺试验依托中建钢构武汉蔡甸职 地上结构、装修工程的施工顺序。
地下工程包括基工宿舍楼。
坑支护、土方开挖、地下结构施工等,一般采用传统2总体思路 的大开挖、复合喷锚、桩锚体系、内支撑体系以及逆该技术基本原理为:地下室地面预筑,通过特 作法等。
传统施工方法的擎端是工期长、环境影响殊技术实现整体下沉,在下沉过程中,地上结构同 大,特别是临时支护结构使用后被废弃或拆除,资步施工,即实现上下同步施工,节约工期。
技术原 源浪费大。
且施工过程中受天气、周边环境影响,理如图1所示,具体步骤分解如下。
安全风险不可忽视。
1)步骤1利用地下室底板基础梁(底板先不 基于改变地下室施工过程中的诸多不确定因浇筑)形成水平网格结构;在工程桩和水平网格结 素对工期、环境以及造价的影响,参考沉井沉箱施构之间设置可周转拆卸的临时顶托桩,形成“工程 工原理,利用在建结构自身作为基坑支护,提出一桩+顶托桩+网格结构”的承托体系。
种创新绿色房屋建造方法-地面预筑、弹性顶2)步骤2地下室在地面预筑,同时继续施工 上部结构。
: *中国建筑股份有限公司课题(CSCEC-2013-Z-9)3)步骤3结合具体情况进行土方开挖后,在 [作者简介]张瑶,教授级高级工程师,E-mail:zhangk@cscec3b.临时顶托桩和水平网格承托之间置换弹性下沉装 【收稿日期]2014-09-15
万方数据
4施工技术第44卷
设计标高设计标高设计标高 +0.000网格结构±0.00±0.000+0.000 顶托桩 工程桩
图1原理示意 Fig.1 Schematic diagram of principle 置,交替微差下沉。
保工程安全。
4)步骤4最终将建...