2013年6月下施工技术 第42卷第12期CONSTRUCTION TECHNOLOGY61 DO1:10. 7672/sgjs2013120061 峡江水利枢纽工程坝顶预制梁架设技术
韩振宝,贾群超,郭宇 (武警水电第二总队第五支队,江苏常州213135) [摘要】江水利枢纽工程预制梁架设施工现场条件复杂,不具备预制梁吊装条件,无法形成坝顶运梁道路,需架 设贝雷架作为临时通道。
介绍了峡江水利枢纽工程坝顶混凝土预制梁架设的施工技术,从方案选择、架桥机选型 以及架设过程中各项技术措施的落实等几方面闸述了坝顶预制梁架设的特点和技术要点。
[关键词】水利枢纽工程;预制梁;架桥机;吊装;施工技术 [中图分类号】TU758【文献标识码】A[文章编号]1002-8498(2013)12-0061-04 ConstructionTechnologyforPrefabricated GirderErection atthe Top of Dam in Xiajiang Hydro-junction Project Han Zhenbao,Jia Qunchao,Guo Yu (No.5 Detachment,No.2 Hydropower Force of Armed Police,Changzhou,Jiangsu 213135,China) Abstract;Because of plex construction site conditions in erecting of prefabricated girder in Xiajiang Hydro-junction project to have no method to build road for transporting the girder, which result in the girder cannot be hoisted, so the Bailey truss need to be erected as the temporary road. This paper junction project,and shows characteristics on prefabricated girder erection from the aspects of scheme selection, selection of bridge erecting machine and erection process,etc. Key words:hydro-junction project; prefabricated girder; bridge erecting machine;hoists; construction 1工程概况差,同时中间还设有3.6mx3.5m的油缸支座二期 峡江水利枢纽工程预制梁架设施工位于左岸6凹槽,架桥机无法直接行走至下游进行预制梁吊 孔泄水闸闸墩顶部及门库坝段边墙顶部,设计有坝装。
泄水闸坝顶布置如图1所示。
顶公路梁、门机轨道梁、电缆沟梁、液压管道沟梁、2预制梁总体架设方案 滑触线沟梁,依次自上游向下游布置。
主要工程量2.1架桥设备简介 为泄水闸坝顶公路梁15根、泄水闸门机轨道梁242.1.1架桥机选型 根、泄水闸电缆沟梁24根、泄水闸液压管道沟梁12预制梁架设最大吊装质量为90.41t(门库门机 根、泄水闸划触线沟梁24根;门库门机轨道梁4根、轨道梁),采用步履式架桥机(JQV10030A.00 划触线沟梁2根。
型)架设,吊装安全储备系数100/90.41=1.106。
预制梁架设施工主要难点为现场施工条件复架桥机主要技术参数如表1所示。
杂。
坝顶上闸首间至门库至泄水闸4号闸墩之间为2.1.2JQIV100-30A.00型架桥机的主要特点 弧形景观桥,暂不具备预制梁吊装条件,无法形成1)JQIV100一30A.00型架桥机额定起重能力为 坝顶运梁道路,须架设临时贝雷桥架作为临时通100t,适用于跨径为20~30m任意宽度的弯、斜预制 道。
泄水闸闸墩顶部及门库边墩长度达47m,门库梁桥的架设。
架设工艺完善、适应性强、工作效率 段跨度为32m,泄水闸段跨度为16m。
门库门机轨高,可充分满足当前此类桥梁的施工要求。
道梁质量达到90.41t,常规方法难以进行吊装。
而2)该型架桥机主梁采用空间三角桁架,在节点 泄水闸闸墩顶部上游与下游之间存在1.8m的高荷载作用下腹杆受力较小,具有结构合理、受力性 [作者筒介】韩振宝,助理工程师,E-mail:737081603@q.能好、质量轻等显著优点。
[收稿日期]2013-02-263)预制梁架设时起吊、机上横移、大车行走、横 万方数据
...