2014年12月下施工技术 第43卷第24期CONSTRUCTIONTECHNOLOGY47 DOI:10. 7672/sgjs2014240047
湘江边岩隙水及泉眼水综合利用技术
张文强,刘曦,姜和平 (中建二局第一建筑工程有限公司,北京100176)
【摘要】针对湘江沿线独特的地质及水文条件,结合某工程施工过程中所面临的实际情况及积累的实际做法与经 验,从封堵、收集以及利用等方面系统闸释了在中分化岩层地质条件下岩醇水及泉眼水的处理方法。
工程实际应 用中取得了较好的效果,对岩隙水的综合收集利用以及泉眼水的封堵、利用高效实用。
[关键词】绿色施工;岩隙水;泉眼水;封堵;收集 [中图分类号】TV13【文献标识码】A[文章编号】1002-8498(2014)24-0047-03 ComprehensiveUtilizationTechnologyofRockCreviceWater and Spring Water Adjacent toXiangjiang River Zhang Wenqiang,Liu Xi,Jiang Heping (The FirstConstruction Engineering Company Ltd.of China Construction Second Enginering Bureau,Bejng 100176,China) Abstract:Based on the special geological conditions and hydrological conditions of Xiangjiang river, bining with the actual condition and the actual experience and method of some project,the water treatment methods between the rocks and spring at the middle weathered rock are described from the sealing,collecting and utilization aspect. The good effect is obtained in the actual project,and the water prehensive collecting utilization between the rocks and the spring water sealing and utilization are efficient and practical. Key words:green construction; rock crevice water; spring water; sealing; collecting 1工程概况见水位距地面深度为0.7~3.9m,高程为35.10~ 华远金外滩三期项目位于长沙市最繁华的中32.33m,稳定水位与初见水位基本一致;补给来源 心地段,总建筑面积28.2万㎡²,由4栋分别为65,为大气降水和地表生活用水渗透。
②弱承压水,主
商业裙房组成,建筑高度为238.5,220.55,204.65,较丰富;初见水位距地面深度为7.8~11.9m;稳定 211.55m,地下室4层,埋深约20m,最深埋深约水位距地面深度为6.20~9.50m,高程为26.84~ 28m,结构形式为框架核心筒结构,地基基础采用筏31.07m;稳定水位略高于初见水位,承压水头约 板结构,基坑采用大开挖,基坑支护采用止水唯幕2.0m;其补给、排泄区域均不在场地内,场地圆砾层 及护坡桩方式。
仅为其径流通道,水位随季节变化较大。
2应用背景1)项目所处的特殊地质及水文条件及基坑开 本工程所处的地理位置距离湘江岸堤仅30m挖情况,基底岩隙水较为丰富,有收集利用的先决 左右,距离湘江极近,地下水较为丰富,设计中本工条件。
程地下4层,地下室埋深约20m,最深埋深达28m,2)在项目进行筏板基础施工时,整体大开挖基 本工程±0.000绝对标高为37.00m,地下室埋深绝坑内,发现6处泉眼零散分布在基坑内,特别是位于 对标高为17.00m,埋深最深处绝对标高为9.00m。
R1栋核心筒电梯井基坑侧壁上的泉眼和R4栋核 根据湖南省建筑设计院提供的地质勘察报告显示,心筒旁集水井底泉眼,处理难度极大,由于基坑挖 本工程的地下水主要为2层,分别为①上层滞水,初深较深,地下水压极大,在项目施工初期,采用常规 [作者简介]张文强,助理工程师,E-mail:429621387@qq.灌浆封堵效果较差,导致基底垫层防水施工无法开 [收稿日期]2014-04-1...