某剧院钢桁架滑移安装技术
徐刿源 (宁波市镇海区建筑工程安全质量监督站,浙江宁波315200)
[摘要]宁波文化广场项目2号楼(剧院)的观众厅和舞台屋面共有8福钢桁架。
析架端部搁置在剧院屋顶的型钢 混凝土框架梁上,与梁顶的预埋螺栓连接,桁架与桁架间通过次梁连接。
重点介绍了钢桁架分段、现场拼装、提升、 滑移安装、端支座段的安装及焊接等施工工艺。
该施工工艺具有成熟合理、安全性高、工期短、施工成本低等特点。
[关键词]钢结构;桁架;滑移;安装;施工技术 [中图分类号】TU758.11[文献标识码]A[文章编号]1002-8498(2014)14-0152-03 TheSteel TrussSlidingandInstallationTechnology ofaTheatre Xu Shanyuan (Ningbo Zhenhai Area Construction Safety and Quality Supervision Station,Ningbo,Zhejiang 315200,China) Abstract;There were eight steel trusses of the auditorium and stage roofs in the theatre of Ningbo Culture Plaza project.The ending of trusses was set on the steel reinforced concrete beams,which was connected with the embedded bolts, and secondary beams were used between the trusses. The trusses segmentation, assembly on site,lifting,sliding and installation,and the installation and welding of the ending were introduced in detail. This technology has the characteristics of reasonable, safe,short period and low cost. Key words:steel structures; trusses; sliding;installation;construction
1工程概况吊装停机位置,且桁架距地下室边缘的距离太远。
宁波文化广场项目IV标段工程,总建筑面积故不能采取大型起重机直接吊装的方案。
又由于 70458m²,地下1层,地上4层,局部5层,建筑总高单福桁架重,安装高度高,即舞台屋面桁架的最高 度38.3m,工程呈不规则平面。
结构形式为框架结安装标高为36.300m,地下有标高为-15.000m的 构,屋面主要采用钢桁架屋面及自承式钢筋桁架屋深基坑,则其安装绝对高度达到51.300m。
观众厅 面。
2号楼(剧院)的观众厅和舞台屋面共有8钢屋面桁架的最高安装标高为30.130m,地面是阶梯 桁架。
其中观众厅有3桁架(编号为TR1),桁架式观众座椅席。
故也不能采用搭设满堂脚手架高 跨度为33.5m,高为4.7m,单桁架重约37t,安装空拼装的方案。
因此该工程必须采用液压提升、滑 标高为30.130m;舞台有5福桁架(编号为TR2),桁移的安装方案。
架跨度为25m,高为3.52m,单福重约20t,安装标高3施工方法 为36.300m。
3.1施工工艺流程 桁架端部搁置在剧院屋顶的型钢混凝土框架桁架分段制作及运输→现场拼装及检测→平
次梁连接。
桁架位置及结构形式如图1,2所示。
就位固定。
2施工方案选择3.2钢桁架分段 由于钢桁架处于剧院的中间位置,剧院四周的根据钢桁架自身的结构特点,考虑到该工程现 场地条件不好,不能为大型起重机提供可靠的有利场的场地条件及道路运输等情况,将一钢桁架分 成4段在制作车间制作,即桁架两端的端支座各为 [作者简介】徐刻源,高级工程师,国家一级注册建造师,造价工程一段,中间部分桁架平分为2段(见图3)。
师,E-mail:xsyzj@ 21cn.由于在桁架提升时,桁架两端的端支座段还未 [收稿日期】2014-03-19
万方数据
2014 No.14徐刻源:某剧院钢桁架滑移安装技术153
中间段增加临时加固杆件,加固杆件规格为HN500 x200×10×16,材质Q345B(见图3)。
...