施工技术 2013年2月下 72 CONSTRUCTIONTECHNOLOGY 第42卷第4期 DO1:10.7672/sgjs2013040072 武汉新城国际博览中心反吊顶吊装技术 郑宜坤,江腾腾,李炳林,刘鹏 (中建三局装饰有限公司,北京100070) [摘要]以武汉新城国际博览中心檐口屋面反吊顶龙骨安装为例,介绍了吊装技术的主要施工工艺流程。
用 AutoCAD软件进行三维实体建模,并在地面选取若干测量控制点,提高了构件加工和吊装精度。
采用地面整体预 制、分段吊装技术对大型钢龙骨进行吊装,最后进行双曲面铝板龙骨安装和铝板安装。
大大缩短了施工工期、提高 了安装精度和施工质量,取得了显著的社会效益和经济效益。
[关键词]安装;反吊顶;整体预制;分块吊装;施工技术 [中图分类号】TU758.1 [文献标识码】A 【文章编号】1002-8498(2013)04-0072-03 Hoisting of Sprung Roofs in Wuhan New Town InternationalExhibition Center Zheng Yikun,Jiang Tengteng,Li Binglin,LiuPeng (Decoration Company of China Construction 3rd Engineering Bureau,Beijing100070,China) Abstract:Taking the installation of the sprung roof of Wuhan New Town International Exhibition Center as an example, the hoisting construction process is introduced.3D solid model was built using AutoCAD and several control points were selected on the ground to improve the accuracy of ponents manufacturing and hoisting.The large steel keel was constructed by integral prefabrication on the ground and segmented hoisting.After that, the installation of hyperbolic curved aluminium plates and their steel keels were installed.The result shows that the construction method shortened the construction period, enhanced the installation accuracy and quality and obtained good social and economic benefits. Key words:installation;sprung roofs;integral prefabrication;segmented hoisting;construction 1工程概况 武汉新城国际博览中心位于武汉市汉阳区新 五里,是武汉规模最大、功能最完善的会展中心,也 是武汉新区新形象、新特色、新功能的集中展示区。
作为地标建筑,武汉新城国际博览中心是一颗明 珠,是武汉向世界展示的一扇窗,其将在武汉乃至 华中经济快速稳步发展中起到不可限量的作用。
本工程由12个展馆、两个登陆厅、12个“玻璃 盒子”组成,其中展馆檐口反吊顶面板为双曲面铝 板,檐口最高点34.8m(见图1)。
由于净空高度较 图1武汉新城国际博览中心实景 高,反吊顶龙骨的安装是一个难点,传统的做法是 Fig.1Wuhan New Town International Exhibition Center 搭设满堂脚手架作为施工平台,将龙骨提升至施工 平台,在空中进行拼接安装、校核、调整,满足精度 且高空焊接坠落的火花和焊渣都是直接的安全隐 要求后进行弧形铝板安装。
这样的施工方法存在 患,擎端很多。
由于武汉国际博览中心项目工期很 施工工期长、费用高、安装精度难以保证等缺点,而 紧,经过反复论证、修改,决定采用“钢架整体预制、 分段吊装”的施工技术,大大加快了施工速度、缩短 [作者简介]郑宜坤,高级工程师,E-mail:280159819@ [收稿日期]2012-11-19 了施工工期、提高了安装精度、减少了措施费用、减 万方数据
...