2012年3月下施工技术 第41卷第361期CONSTRUCTION TECHNOLOGY55
某住宅工程地下结构墙体钢塑模板施工技术
王卫东,范明,吴庆来,左康 (北京城建五建设工程有限公司,北京100029) [摘要]某住宅小区工程地下结构墙体采用钢塑模板代替小钢模。
分别对钢塑模板、GP70组合钢模板、散拼散装 木模板3种方案进行综合对比分析,确定选择钢塑模板施工。
对模板材料、设计、施工工艺进行详细介绍,施工效 果良好。
混凝土垂直度、平整度、截面尺寸均满足质量验收要求。
[关键词]模板;住宅;地下结构;墙;钢塑模板;螺栓;施工技术 [中图分类号】TU755.2[文献标识码】A[文章编号】1002-8498(2012)06-0055-03 Plastics-steelFormworkConstructionforSome UndergroundWall ofHousing Wang Weidong,Fan Ming,Wu Qinglai,ZuoKang (The Fifth Urban Consruction Engineering Company of Bejing,Beijing 100029,China) Abstract;Plastics-steel formwork is used instead of small steel formwork for some underground wall of housing. The plastics-steel formwork, GP70 posite steel formwork and bulk wood formwork are pared synthetically to assure the plastics-steel formwork. The formwork materials, design and construction process are introduced in detail,and the effect is excellent.The verticality, smoothness and section size can meet quality acceptance requirement. Key words: formwork; housing; underground structures; walls; plastics-steel formwork; bolts; construction 1工程概况组合钢模板水平拼缝多,易缺棱掉角,混凝土观 某住宅小区总建筑面积97818m²,为现浇剪力感质量一般。
质量较重,运输及拆装模板困难,劳 墙结构。
地下2层,地上5~18层。
1~4号楼地下动强度高。
拆模后需对板面清理、刷脱模剂,占用 室层高为3.85m,地上层高2.9m;5,7,9号楼地下塔式起重机吊次多。
可长期周转使用,不易破损, 层高3.7m,地上层高2.8m。
墙厚为200,250,综合成本较低。
③散拼散装(木模板)水平拼缝 300mm,地下墙体展开面积20500m²。
较多,易曲翘不平,飞边凸肋,混凝土观感质量好。
2模板选择质量轻,易运输,拆装方便,施工难度小,前期拼装 地下室墙体模板选择时,分别对钢塑模板、时间长,板面需清理后刷脱模剂,占用塔式起重机 GP70组合钢模板、散拼散装木模板3种模板方案进吊次少。
周转次数少(4次),木材使用量较大,不环 行综合对比:①钢塑模板按墙体高度定尺加工模保。
综合成本较高。
板,无水平模板拼缝;表面平整度、垂直度及截面尺综合以上3种方案对比,本工程地下室墙体模 寸满足规范要求,混凝土观感质量好。
不粘模,易板最终选择钢塑模板方案施工。
清灰,质量轻,不变形,支撑操作方便,一拼而成。
3钢塑模板材料介绍 不需脱模剂,混凝土凝固后,模板与混凝土自动分1)墙体钢塑模板平模宽度主要规格为:100, 离,脱模容易,占用塔式起重机吊次少。
周转次数150,200,250,300,350,400,450,500,550,600mm。
多(20次)、能二次回收利用。
钢塑模板厂家100%高度根据工程墙体实际浇注高度定尺加工(见图 置换,符合国家环保政策,综合成本较低。
②GP701a)。
[收稿日期]2011-12-062)阴角、阳角模板可根据实际施工要求定尺加 [作者简介]王卫东,北京城建五建设工程有限公司总工程师,高级工(见图1b,1c)。
工程师,北京市朝阳区安苑东里三区十号100029,电话:(010)3)板缝拼接专用卡子如图1d所示。
,E-mail wwd514@ 126. ...