2012年10月上施工‘技术 第41卷第374期CONSTRUCTION TECHNOLOGY41
软土地区深基坑不同施工阶段综合支护技术
姜青国,陈临韬,张秀先,彭海峰 (天津二十冶建设有限公司,天津300301)
[摘要]根据沿海软土地区某基坑工程周边环境安全要求,在不同的施工阶段分别采用钻孔灌注桩排桩+止水帷 幕+水泥土搅拌桩暗墩、水泥土搅拌桩挡土墙、钻孔灌注桩排桩+坑内钢支撑的支护体系。
监测结果表明,通过合 理安排支护结构施工、井点降水、土方开挖等工序,使基坑支护结构处于稳定状态,确保了基坑周边环境的安全。
【关键词]地下工程;深基坑;支护;软土;施工技术;监测 [中图分类号】TU753【文献标识码】A[文章编号11002-8498(2012)19-0041-04
Comprehensive Support Technology in Different Stage of Deep Foundation Excavation in Soft Soil Area Jiang Qingguo, Chen Lintao, Zhang Xiuxian, Peng Haifeng ( Tianjin No. 20 Metallurgical Construction Co. ,Ltd. ,Tianjin 300301 ,China)
Abstract: According to the safety requirement of a deep foundation excavation engineering in coastal soft soil area, different support methods were adopted in different stages of construction. Specifically, row of bored piles with water proof curtain and cement mixing pile submerged pier, cement mixing pile retaining wall and row of bored piles with steel supports have been adopted. Site monitoring data shows that by proper arrangement of construction process, such as structural construction, well-points dewatering, and soil excavation, the supporting structure was maintained stable and the foundation excavation safety was ensured. Key words:underground ; deep foundation excavation; supports; soft soil; construction ; monitoring
1~ 工程概况厂房(檐口标高47m)、检验楼、电气室(4层框架结 天津鞍钢天铁薄板有限公司位于天津空港经构)、100t应急水塔(钢筋混凝土倒锥形水柜,水柜 济区,一期工程于2008年建成投产,二期工程包括标高57.000m)等建筑物。
连退生产线工程基坑南 连退生产线工程、彩涂工程、电镀锌工程。
连退生侧为冷轧南二路,道路宽10m,路对面有110kV变电 产线工程为单层钢排架厂房,灌注桩基础,主线为站、水处理系统、球罐区。
施工工艺总平面如图1 单跨,成品库为两跨,主轧跨跨度为33m,檐口标高所示。
45m:成品库跨度为18m.檐口标高22m,车间总长2 工程地质条件 623m,主厂房为独立柱基础,柱基础深度为-6.600~2.1地下水位 -7.100m。
高跨内为设备基础,人口段底标高建设场地初见水位埋深 2.300~3.000m,相当 -7.400m,人口活套底标高-13.445m,退火炉基础于标高1.790~0.550m,静止水位埋深1.500~ 底标高-0.900m,出口活套底标高-13.445m,检查2.500m,相当于标高2.490~1.480m。
场地浅层地 活套底标高-14.155m,出口段底标高-7.400m。
南下水属潜水类型,水位随季节有所变化。
侧为主电室,主电室底标高一6.000m,灌注桩基础。
2.2地质情况 连退生产线工程基坑北侧为冷轧南一路,基坑根据天津市勘察院提供的地质资料,连退机组 距离道路路石最近处约2.8m,道路宽7m,道路对面第13号勘探孔勘测数据显示各层土的性质如表1 仅3.5...